Disaster recovery is the part of contingency planning that covers
the worst case: the place a system runs in has been lost or is out
of reach for a long time, and the system has to be rebuilt somewhere
else from copies. NIST's Contingency Planning Guide for Federal
Information Systems, SP 800-34 Revision 1 from 2010, defines the
disaster recovery plan as a written plan for recovering one or more
information systems at an alternate facility after a major hardware
or software failure or the destruction of facilities. Its scope is
narrow. The guide reserves it for major disruptions, usually
physical ones, that deny access to the primary facility for an
extended period, and it covers only the disruptions that require
relocation.

That narrowness sets it apart from its neighbours. An information
system contingency plan, in the guide's vocabulary, restores a
single system wherever it happens to stand, whether after a failed
disk or a corrupted database. The disaster recovery plan is tied to
a site: it moves operations to the alternate location, and from
there each system is brought up by its own contingency plan. A plan
for one database and a plan for losing a whole data centre, cloud
region or provider account are different documents with different
owners, and confusing the two is how a company ends up with neither.

Three measures turn the plan from an intention into something that
can be checked. Maximum tolerable downtime (MTD) is the total length
of outage the system's owner is willing to accept. The recovery time
objective (RTO) is the longest a system resource can stay
unavailable before the damage to other systems and to the business
becomes unacceptable, and because interrupted work also has to be
reprocessed afterwards, the guide says the RTO must normally be
shorter than the MTD. The recovery point objective (RPO) looks
backwards: it is the point in time before the outage to which data
can be recovered from the most recent backup copy, and it expresses
how much lost data the business can live with. Put simply, the RTO
is how long you are down and the RPO is how much work you lose.

The alternate site comes in grades. A cold site offers space and
infrastructure only, a warm site is partly equipped, and a hot site
is fully equipped and staffed. The guide adds mobile sites, which in
many cases can be delivered within 24 hours before setup begins, and
mirrored sites, the most expensive option and the one it credits
with "virtually 100 percent availability". Cold sites are the
cheapest to maintain and may take substantial time to equip. A
second cloud region or a second provider plays the same role for
most software today, and the trade-off between what stands ready and
what it costs to keep it ready is the same.

Why it matters

A backup is a copy, and a copy on its own runs nothing. Getting from
the copy to a working system also takes the software that reads it,
the keys that decrypt it, servers and a network to run it on, the
configuration that ties them together, and someone who knows the
order to do it in. Any of those that existed only in the lost site
was lost with it. Disaster recovery is the discipline of making sure
that all of them survive the same event, and that the path from copy
to service has been walked before anyone needs it.

Recoverable data is only as recent as the last copy that restores,
whatever RPO the backup schedule is meant to meet. A nightly job
that has failed silently for a week leaves a week’s data at risk,
whatever the policy document says. NIST's guide makes the same point
about tape, recommending that backups be tested regularly to confirm
that the data is stored correctly and that the files can be
retrieved without errors or loss. A green status light on a backup
job proves that something was written. Only a restore proves it can
be read back.

The plan also decays. People leave, servers are replaced, providers
redesign their consoles, and the passwords in the runbook expire. Of
the seven steps NIST lays out for contingency planning, the last two
are testing, training and exercises, and plan maintenance; the guide
wants the plan to be a living document, reviewed at least once a
year and whenever the system or the resources used for recovery
change significantly. A plan that has never been rehearsed tends to
fail on details nobody thought to write down: the order the services
must start in, a DNS record with a day-long time to live, the one
credential that was stored on the machine that is gone.

For software teams, the disaster is often an account rather than a
building. A deleted cloud project, a compromised administrator
login, a suspended provider account or a destructive command run
against production removes access to the system as thoroughly as a
flood does. Standby servers are no protection against the last of
these, since a standby applies a mistaken `DROP TABLE` within
moments, exactly as it applies every other change.

What it looks like in practice

For a PostgreSQL database, a recovery point far shorter than the gap
between two backups comes from continuous archiving of the
write-ahead log (WAL) on top of a base backup. The server copies
each finished WAL segment somewhere safe, and a restore replays
those segments onto the base backup up to any chosen moment since
the base backup was taken:

```ini
i# postgresql.conf on the protected server		engineer.company	70
wal_level = replica
archive_mode = on
archive_command = 'test ! -f /mnt/archive/%f && cp %p /mnt/archive/%f'
```

To restore, a base backup is unpacked into a fresh data directory,
an empty file named `recovery.signal` is placed in it, and the
recovery settings say where the archive is and where to stop:

```ini
restore_command = 'cp /mnt/archive/%f %p'
recovery_target_time = '2026-03-10 17:14:00+01'
recovery_target_action = 'pause'
```

The PostgreSQL documentation tells the story these settings exist
for: someone drops a critical table at 5:15 on a Tuesday evening,
notices on Wednesday at noon, and restores to 5:14. Pausing is the
default once the target is reached, so that queries can confirm it
is the right moment before the server is promoted to accept
connections; if it is not, the server is shut down, given a later
target and started again. The chosen recovery time must be later
than the completed base backup, and the documentation advises
setting up and testing the archiving before the first base backup is
taken. When recovery completes, the server removes `recovery.signal`
so that it does not enter recovery again by accident.

Engineer ApS offers backup and disaster recovery as a service,
described as backups that are tested rather than assumed and a
written plan for the morning a server does not come back. Two
portfolio pages show what that means. In backups and disaster
recovery as code, from 2025, backup retention was set in Bicep
beside the database, so point-in-time restore is part of the
template instead of a setting someone once clicked in a portal, and
the environment around the database was defined as code too, because
a database restored into an environment rebuilt from memory is
hardly recovered. The recovery position was then audited and written
down with its gaps named: geo-redundancy was switched off, and the
recovery time objective was proposed rather than measured, since no
drill had been run.

The company's backup and restore-test automation was designed to
extend recovery beyond a provider snapshot. An Ansible role installs
restic scripts and systemd units for a database dump where
configured, encrypted deduplicated snapshots to storage at another
provider over SFTP, retention pruning and integrity checks. A
separate monthly workflow restores a known file to a scratch
location and compares its bytes. Backup and restore have separate
success signals, the passphrase comes from a protected file, and
timers depend on a configured repository. Those controls are
implemented; a live recovery is a separate deliverable. The
implementation record dated

2026-10-27 says the timers were disabled without a repository and
records no completed live restore, so it supports the automation
work rather than a recovery-time commitment or a claim that the
company can already lose the host safely.

Where it goes wrong

The backup has never been restored. A job that reports success every
night says nothing about whether its output can be read, decrypted
and loaded, and the first real restore is a poor moment to find out.
Schedule restores the way you schedule backups: an automated check
that pulls known data out and compares it, and a full restore into a
clean environment often enough that the time it takes is a measured
number.

The copy shares the original's fate. A snapshot in the same cloud
account, a backup disk in the same rack or an archive bucket behind
the same administrator login goes down with whatever takes the
primary. NIST's guide asks for offsite storage and alternate sites
to be chosen for how unlikely they are to be hit by the same
disaster. Keep at least one copy with another provider or in another
account with separate credentials, and keep the decryption keys
somewhere that does not depend on the systems they protect.

Only the data was planned for. Restoring a database is a small part
of bringing a service back if the servers, firewall rules, DNS,
certificates and secrets around it have to be recreated from memory.
Define the environment in version-controlled infrastructure as code,
and make rebuilding it part of the drill, not only loading the data.

The objectives are guesses. An RTO written into a document without a
drill behind it is a proposal, and an RPO that assumes every backup
succeeded is optimistic. Measure both in an exercise. NIST separates
tabletop exercises, which are discussion only and deploy no
equipment, from functional exercises that simulate operations, up to
full-scale ones that cover every element of the plan; the numbers
come from the second kind.

A standby is counted as a backup. A standby server or a
geo-replicated database protects against losing hardware, but it
copies deletions, corruption and files encrypted by ransomware as
faithfully as good writes. Keep point-in-time copies that a mistake
on the primary cannot reach, and keep them for longer than it
usually takes to notice a mistake.

The plan describes last year's system. A runbook that lists retired
servers, people who have left and passwords that no longer work
slows a recovery down instead of guiding it. Review the plan after
every significant change and after every drill, record what the
drill got wrong, and review the parts that change most often, such
as contact lists, more often still, as NIST also recommends.

Further reading

  * SP 800-34 Rev. 1, Contingency Planning Guide for Federal
Information Systems — the full guide: how it defines and scopes the
DRP, the seven planning steps, MTD, RTO and RPO, alternate sites and
exercise types, with plan templates.

  * Continuous Archiving and Point-in-Time Recovery (PITR) —
PostgreSQL 18's chapter on WAL archiving, base backups and restoring
to a chosen moment.

  * Write Ahead Log — the configuration reference for
`archive_command`, `restore_command` and the recovery target
settings.

hThis page on the web	URL:https://engineer.company/glossary/disaster-recovery/	engineer.company	70