# Disaster recovery

## What it is

Disaster recovery is the part of contingency planning that covers the worst
case: the place a system runs in has been lost or is out of reach for a long
time, and the system has to be rebuilt somewhere else from copies. NIST's
Contingency Planning Guide for Federal Information Systems, SP 800-34 Revision 1
from 2010, defines the disaster recovery plan as a written plan for recovering
one or more information systems at an alternate facility after a major hardware
or software failure or the destruction of facilities. Its scope is narrow. The
guide reserves it for major disruptions, usually physical ones, that deny access
to the primary facility for an extended period, and it covers only the
disruptions that require relocation.

That narrowness sets it apart from its neighbours. An information system
contingency plan, in the guide's vocabulary, restores a single system wherever
it happens to stand, whether after a failed disk or a corrupted database. The
disaster recovery plan is tied to a site: it moves operations to the alternate
location, and from there each system is brought up by its own contingency plan.
A plan for one database and a plan for losing a whole data centre, cloud region
or provider account are different documents with different owners, and confusing
the two is how a company ends up with neither.

Three measures turn the plan from an intention into something that can be
checked. Maximum tolerable downtime (MTD) is the total length of outage the
system's owner is willing to accept. The recovery time objective (RTO) is the
longest a system resource can stay unavailable before the damage to other
systems and to the business becomes unacceptable, and because interrupted work
also has to be reprocessed afterwards, the guide says the RTO must normally be
shorter than the MTD. The recovery point objective (RPO) looks backwards: it is
the point in time before the outage to which data can be recovered from the most
recent backup copy, and it expresses how much lost data the business can live
with. Put simply, the RTO is how long you are down and the RPO is how much work
you lose.

The alternate site comes in grades. A cold site offers space and infrastructure
only, a warm site is partly equipped, and a hot site is fully equipped and
staffed. The guide adds mobile sites, which in many cases can be delivered
within 24 hours before setup begins, and mirrored sites, the most expensive
option and the one it credits with "virtually 100 percent availability". Cold
sites are the cheapest to maintain and may take substantial time to equip. A
second cloud region or a second provider plays the same role for most software
today, and the trade-off between what stands ready and what it costs to keep it
ready is the same.

## Why it matters

A backup is a copy, and a copy on its own runs nothing. Getting from the copy to
a working system also takes the software that reads it, the keys that decrypt
it, servers and a network to run it on, the configuration that ties them
together, and someone who knows the order to do it in. Any of those that existed
only in the lost site was lost with it. Disaster recovery is the discipline of
making sure that all of them survive the same event, and that the path from copy
to service has been walked before anyone needs it.

The RPO is set by the last copy that restores, not by the backup schedule. A
nightly job that has failed silently for a week leaves an RPO of a week,
whatever the policy document says. NIST's guide makes the same point about tape,
recommending that backups be tested regularly to confirm that the data is stored
correctly and that the files can be retrieved without errors or loss. A green
status light on a backup job proves that something was written. Only a restore
proves it can be read back.

The plan also decays. People leave, servers are replaced, providers redesign
their consoles, and the passwords in the runbook expire. Of the seven steps NIST
lays out for contingency planning, the last two are testing, training and
exercises, and plan maintenance; the guide wants the plan to be a living
document, reviewed at least once a year and whenever the system or the resources
used for recovery change significantly. A plan that has never been rehearsed
tends to fail on details nobody thought to write down: the order the services
must start in, a DNS record with a day-long time to live, the one credential
that was stored on the machine that is gone.

For software teams, the disaster is often an account rather than a building. A
deleted cloud project, a compromised administrator login, a suspended provider
account or a destructive command run against production removes access to the
system as thoroughly as a flood does. Standby servers are no protection against
the last of these, since a standby applies a mistaken `DROP TABLE` within
moments, exactly as it applies every other change.

## What it looks like in practice

For a PostgreSQL database, a recovery point far shorter than the gap between two
backups comes from continuous archiving of the write-ahead log (WAL) on top of a
base backup. The server copies each finished WAL segment somewhere safe, and a
restore replays those segments onto the base backup up to any chosen moment
since the base backup was taken:

```ini
# postgresql.conf on the protected server
wal_level = replica
archive_mode = on
archive_command = 'test ! -f /mnt/archive/%f && cp %p /mnt/archive/%f'
```

To restore, a base backup is unpacked into a fresh data directory, an empty file
named `recovery.signal` is placed in it, and the recovery settings say where the
archive is and where to stop:

```ini
restore_command = 'cp /mnt/archive/%f %p'
recovery_target_time = '2026-03-10 17:14:00+01'
recovery_target_action = 'pause'
```

The PostgreSQL documentation tells the story these settings exist for: someone
drops a critical table at 5:15 on a Tuesday evening, notices on Wednesday at
noon, and restores to 5:14. Pausing is the default once the target is reached,
so that queries can confirm it is the right moment before the server is promoted
to accept connections; if it is not, the server is shut down, given a later
target and started again. The chosen recovery time must be later than the
completed base backup, and the documentation advises setting up and testing the
archiving before the first base backup is taken. When recovery completes, the
server removes `recovery.signal` so that it does not enter recovery again by
accident.

Engineer ApS offers [backup and disaster recovery](/services/backup-recovery/)
as a service, described as backups that are tested rather than assumed and a
written plan for the morning a server does not come back. Two portfolio pages
show what that means. In
[backups and disaster recovery as code](/portfolio/implemented-backups-and-disaster-recovery-as-code/),
from 2025, backup retention was set in Bicep beside the database, so
point-in-time restore is part of the template instead of a setting someone once
clicked in a portal, and the environment around the database was defined as code
too, because a database restored into an environment rebuilt from memory is
hardly recovered. The recovery position was then audited and written down with
its gaps named: geo-redundancy was switched off, and the recovery time objective
was proposed rather than measured, since no drill had been run.

In
[backups that have actually been restored](/portfolio/backups-that-have-actually-been-restored/),
from September 2026, the starting point was a company whose repositories,
database and website sat on one cloud instance, with the provider's snapshot as
the entire recovery position: held in the same account as the machine, not
encrypted by the company, and never once restored. The replacement runs on a
[systemd](/glossary/#systemd) timer: a database dump where there is one, then an
encrypted, deduplicated restic snapshot to storage at a different provider over
SFTP, then a retention prune and an integrity check. A dead-man's switch is
pinged only when the run succeeds, so silence raises the alert. Every month a
restore drill pulls a known file out of the repository and compares it. The
page's claim that the company can lose the host and get its data back rests on
that monthly restore, not on last night's backup.

## Where it goes wrong

**The backup has never been restored.** A job that reports success every night
says nothing about whether its output can be read, decrypted and loaded, and the
first real restore is a poor moment to find out. Schedule restores the way you
schedule backups: an automated check that pulls known data out and compares it,
and a full restore into a clean environment often enough that the time it takes
is a measured number.

**The copy shares the original's fate.** A snapshot in the same cloud account, a
backup disk in the same rack or an archive bucket behind the same administrator
login goes down with whatever takes the primary. NIST's guide asks for offsite
storage and alternate sites to be chosen for how unlikely they are to be hit by
the same disaster. Keep at least one copy with another provider or in another
account with separate credentials, and keep the decryption keys somewhere that
does not depend on the systems they protect.

**Only the data was planned for.** Restoring a database is a small part of
bringing a service back if the servers, firewall rules, DNS, certificates and
secrets around it have to be recreated from memory. Define the environment in
version-controlled infrastructure as code, and make rebuilding it part of the
drill, not only loading the data.

**The objectives are guesses.** An RTO written into a document without a drill
behind it is a proposal, and an RPO that assumes every backup succeeded is
optimistic. Measure both in an exercise. NIST separates tabletop exercises,
which are discussion only and deploy no equipment, from functional exercises
that simulate operations, up to full-scale ones that cover every element of the
plan; the numbers come from the second kind.

**A standby is counted as a backup.** A standby server or a geo-replicated
database protects against losing hardware, but it copies deletions, corruption
and files encrypted by ransomware as faithfully as good writes. Keep
point-in-time copies that a mistake on the primary cannot reach, and keep them
for longer than it usually takes to notice a mistake.

**The plan describes last year's system.** A runbook that lists retired servers,
people who have left and passwords that no longer work slows a recovery down
instead of guiding it. Review the plan after every significant change and after
every drill, record what the drill got wrong, and review the parts that change
most often, such as contact lists, more often still, as NIST also recommends.

## Further reading

- [SP 800-34 Rev. 1, Contingency Planning Guide for Federal Information Systems](https://csrc.nist.gov/pubs/sp/800/34/r1/upd1/final)
  — the full guide: how it defines and scopes the DRP, the seven planning steps,
  MTD, RTO and RPO, alternate sites and exercise types, with plan templates.
- [Continuous Archiving and Point-in-Time Recovery (PITR)](https://www.postgresql.org/docs/18/continuous-archiving.html)
  — PostgreSQL 18's chapter on WAL archiving, base backups and restoring to a
  chosen moment.
- [Write Ahead Log](https://www.postgresql.org/docs/18/runtime-config-wal.html)
  — the configuration reference for `archive_command`, `restore_command` and the
  recovery target settings.

<https://engineer.company/glossary/disaster-recovery/>